Cluttons has been appointed to provide project & cost management services for the comprehensive refurbishment of the Grade II* Garrick Club for their Masterplan Project.
Outcome
The multi-phased works, all carried out whilst the Club remains open to its members, will create new members’ facilities, improve access and circulation, new private dining suites and nine additional bedrooms.
Cluttons are responsible for:
Managing all aspects of the project, including establishing the project brief and the project team
Managing the planning & listed building consent process
Contractor selection, tender and appointment
Supervising the complex construction activities on site including acting as contract administrator
How we helped
The project posed many challenges to the club, its operations and its members. We have worked closely with the club and carried out detailed logistical planning to ensure that the major construction works are carried out in a manner that enables the members to continue to enjoy the club’s facilities whilst the works are being carried out.
Our input provided solutions including:
A detailed operational assessment identifying the Club’s critical operational activities
Outlining a preferred construction programme & phasing, addressing the significant access challenges
A comprehensive procurement review
Managing enabling works contracts
Preparing and negotiating Party Wall awards
Related services
Neighbourly matters
Whether acting on behalf of a building owner or an adjoining owner, our key priority is to mitigate risks to neighbouring buildings from structural movement or fire spread.
Project management
Whether a developer, tenant or landlord our project management team provides you with the certainty needed in managing complex and sustainable projects in today’s pressurised business environment.