Cluttons were instructed as project and cost manager for Tesco Mobile to oversee a CAT B, 13,000 sq ft office refurbishment.
How we helped
We made an accelerated start on site and managed the contractor open book procurement.
A series of defects were identified pre-start on site to the landlord plant. These were clearly documented and issued to the landlord for remedial action to be taken. We supported the CAT B works proceeding with the landlord working to resolve the defects which led to a positive resolution, without delay to the client occupation or final product.
Outcome
The creation of a new office space that exceeded end user requirements, it was completed on tine and under budget despite client changes and additional scope.
“Philip’s ability to adapt and meet the demands of a very challenging fit-out programme was key. Everyone involved has been complimentary about Cluttons.”